High Speed 2 Line

Department for Transport written question – answered am ar 14 Chwefror 2024.

Danfonwch hysbysiad imi am ddadleuon fel hyn

Photo of Lord Framlingham Lord Framlingham Ceidwadwyr

To ask His Majesty's Government what estimate they have made of the cost of completing the first phase of HS2; and what is the projected completion date.

Photo of Lord Davies of Gower Lord Davies of Gower Parliamentary Under-Secretary (Department for Transport)

As set out in the Network North command paper, for the historic Phase 1 scope DfT officials have estimated a provisional range of £45 billion to £54 billion.

Given these cost assessments were made before the decision was taken to cancel Phase 2, the Department has asked HS2 Ltd to consider the revised scope of the project and provide an action plan on how it will deliver this at the lowest reasonable cost. We will be able to provide more information in due course.

Delivery remains on track for the initial high-speed services between Old Oak Common in west London and Birmingham Curzon Street by 2029 to 2033. An updated delivery-into-service range for services to Euston will be provided in due course.