To ask the Secretary of State for Defence, when construction work on Box A of Project Pegasus at the Atomic Weapons Establishment started.

Photo of Philip Dunne Philip Dunne The Parliamentary Under-Secretary of State for Defence

Pegasus is the replacement Highly Enriched Uranium component manufacturing and storage facility, and forms part of the Government's programme of investment in the Atomic Weapons Establishment sites.

Preparatory work on Box A started in May 2013 and construction work began in August 2013.