A96 Dualling (Compensation)

Part of Portfolio Question Time – in the Scottish Parliament am 2:30 pm ar 6 Chwefror 2025.

Danfonwch hysbysiad imi am ddadleuon fel hyn

Photo of Fiona Hyslop Fiona Hyslop Scottish National Party 2:30, 6 Chwefror 2025

First as the Minister for Transport and now, as Cabinet Secretary for Transport, I have progressed the A96 Inverness to Nairn project, including the Nairn bypass. I have ensured that we have made progress on completing the made orders and acquiring the land. We are acquiring the land because we intend to dual that part of the A96 first. That is what is happening.

As I explained to the public meeting in Nairn last summer, the timetable for dualling will be determined by two things. The first is the method of procurement, whether it is capital procurement or through a mutual investment model. We are considering the mutual investment model for the A96 part of the road—which we have just been discussing—and for the A9. On completion of that consideration, we will be in a position to determine the timetable, which I will be happy to share with the Parliament.

The other consideration is whether one procurement process will be completed for the whole project or whether the contracts will be separated for different parts. A strong argument was put to me at the public meeting in Nairn that the Nairn bypass might be done separately and differently. All those things will impact on the timetable, and we will consider them. When we have managed to assess all those points, I will come back to the Parliament.