Clause 35 - Lapse of building control approval etc

Part of Building Safety Bill – in a Public Bill Committee am 3:30 pm ar 21 Medi 2021.

Danfonwch hysbysiad imi am ddadleuon fel hyn

Photo of Christopher Pincher Christopher Pincher Minister of State (Department for Levelling Up, Housing and Communities) 3:30, 21 Medi 2021

This clause replaces section 32 of the Building Act 1984, that bell-bottom flare and platform-shoe Act that we need to reform in order to make it more competent. I do not mean to be flippant, but we need to make it more appropriate to the modern day. This clause also amends section 52 and schedule 4 of the Act, to simplify the process under which a building control approval given by a building control authority, or an initial notice issued by a registered building control approver, or a public body’s notice, lapses if work has not started after three years.

The changes will bring the Building Act in line with how unused planning permissions lapse automatically after three years if work has not started. Currently, if work has not started after three years, a local authority can issue a notice that any plans approval issued for that work has no effect, or to cancel any initial notice that has been issued for that work.

Rather than placing the onus on the local authority to identify and take proactive action to issue a notice that the building control approval has no effect, or to cancel the notice, the new section 32, and amended sections 52 and schedule 4, allow for the approval or notices to lapse automatically. This simplifies the system and saves the local authority the administration of having to issue the notice of cancellation.