My Lords, once again I thank the Minister for his explanation of the regulations before the House. This instrument widens the scope of the 2013 regulations to include both the industrial emissions directive, IED, which applies to large combustion plant over 50 megawatts, and the medium combustion plant directive, MCPD, which applies to plant with an individual thermal input of up to 50 megawatts.
Previously, the control of pollutant emissions from large combustion plant was not seen to be relevant for offshore facilities. Controls from the MCPD need to be extended to regulating emissions harmful to human health and the environment. The objective of these regulations is to control atmospheric emissions from offshore combustion plant that previously had been limited to onshore facilities under the Department for Environment, Food and Rural Affairs. The Explanatory Memorandum explains:
“The amending of the existing Regulations and widening of permit requirements are already familiar to offshore operators, who will receive a single permit covering all the qualifying combustion plant for each installation”.
We welcome this rationalisation. The memorandum further explains that OPRED, the offshore regulator mentioned in the previous regulations, will have its duties extended to implementing the instrument and will be able to recover its costs through fees charged for permits. Rather like the noble Lord, Lord Teverson, I assume from the previous regulations that OPRED will have the sanctions we have just approved to ensure compliance.
I understand that there are two large offshore plants over 50 megawatts, as the Minister explained, and 13 smaller offshore plants covered by the MCPD. However, the memorandum explains that implementation will apply to plants covered by the MCPD according to a timetable, whether they are new or already in existence. Further expanding on the words of the noble Lord, Lord Teverson, new plants will need a permit from
The consultation merely gave rise to issues regarding the ease of monitoring and access to exhaust stacks on existing facilities. I am glad to see that the department is aware of this and that OPRED will be taking a pragmatic approach. However, there could well be issues regarding the monitoring of carbon monoxide for its effects on human health. Can the Minister assure the House that this pragmatic approach will not give rise to possible monoxide risks to human health? With the assurance that these issues are not material, I am content to approve the regulations today.