Part of Oral Answers to Questions — Ministry of Works – in the House of Commons am 12:00 am ar 26 Ebrill 1948.
On 30th March the Mobile Labour Force was engaged in erecting the following buildings or works; the estimates of final cost are:
Type. | Number. | M.L.F. estimated final cost. |
£ | ||
New traditional houses, including roads, sewers and all services | 107 | 268,086 |
Erection of prefabricated houses | 343 | 397,070 |
Totally destroyed dwellings | 619 | 1,020,093 |
Hutted sites for school meals and classrooms | 29 | 204,851 |
Temporary office building sites | 9 | 1,467,375 |
Employment Exchanges | 1 | 87,268 |
Constructional work on Government Factories and Research Establishments | 9 | 2,226,070 |