Temporary Houses (Erection Time)

Oral Answers to Questions — Ministry of Works – in the House of Commons am 12:00 am ar 23 Gorffennaf 1946.

Danfonwch hysbysiad imi am ddadleuon fel hyn

Photo of Mr William Shepherd Mr William Shepherd , Bucklow 12:00, 23 Gorffennaf 1946

asked the Minister of Works what has been the average time taken for the erection of temporary houses, including the time required for the preparation of the site.

Photo of Mr George Tomlinson Mr George Tomlinson , Farnworth

From the beginning of site preparation to the occupation of the house, the average time taken has been about nine months. The period is being reduced as the rate of supply of certain items improves.

Photo of Mr William Shepherd Mr William Shepherd , Bucklow

Can the right hon. Gentleman say how this time compares with the estimate originally given?

Photo of Sir Henry Legge-Bourke Sir Henry Legge-Bourke , Isle of Ely

Can the right hon. Gentleman say what period is involved when the sites are prepared and no work is going on, before building commences?

Photo of Mr George Tomlinson Mr George Tomlinson , Farnworth

In that period of nine months that I have given, about three months.